CRITERIA FOR SHIPPING TELESCOPE TO WASHINGTON CAMP
TSU proposed the following criteria for certifying that the 2-m telescope is ready for shipping to Arizona. They are based on a verbal agreement reached with NASA's oversight committee on 21 October 1999, and they were presented to NASA in the monthly progress report for the 2-m telescope project for September, 1999. There being no objection to them as of 1 March 2000, they are therefore adopted.
The physical pieces of the telescope shall fit together with all interferences remaining from design or manufacture eliminated. TSU shall either verify the fit of any parts not shipped with the telescope (e.g., possibly the secondary-mirror cell and the instrument heads) or measure their mechanical interfaces accurately enough to have them fit in the field. Exceptions: TSU reserves the prerogative of fitting parts of the instrument head, such as cabling for the fiber optics, until the telescope is in Arizona.
As of 9 March 2000 this criterion is satisfied for the whole telescope structure. All mechanical parts fit together and the indexing pins for the secondary-mirror cell and instrument head are in place and tested for proper fit.
The oil bearings shall support the telescope sufficiently to allow it to move freely in azimuth, even when hot, and the leakage of oil shall be slight enough to allow the telescope to work all night without maintenance. Specific requirements and tests follow.
We have run the oil bearings for an average of 1.5 hrs/day for 3 days a week over the past two months (Mid January through mid March, and earlier) for a total of 36 hours without losing more than a quart of oil. Furthermore, as a test designed to detect problems with overheating in the bearings and drives, we ran the telescope for 8 straight hours with both axes running continuously at moderate rates on 16 March, and the telescope worked perfectly well.
We have amassed the materials for these modifications as of mid March, 2000, and plan making these modifications when the telescope is partially disassembled for packing. The specific modifications are (1) recutting the seals around the pads to reduce the clearance between them and the supported surface (from 0.005 inches to about 0.001 inches) and (2) putting in provisions to compensate the bearings with capillary tubes instead of the current orifices.
The telescope has passed these tests many times as of 9 March, 2000, both with the hand-held controller and under under computer control. We have driven the telescope over its complete range in both fast driving and slewing rates, recording the demand on the motors to run the axes, and find demands of the order 20-25 percent for both axes at both rates. Plots of the demand vs. position are given here: Azimuth-tracking (AZ1 (forward), AZ2 (reverse), AZ3 (reverse), and AZ4 (forward)); Azimuth-slewing (AZ1S (forward), AZ2S (reverse), AZ3S (reverse), and AZ4S (forward)); Zenith Distance -tracking (ZD1 (to horizon), ZD2 (to zenith)); Zenith Distance-slewing (ZD1S (to horizon) and ZD2S (to zenith)). Because of the orientation of the motors, both azimuth and zenith distance increase toward more negative encoder counts.
The telescope has passed these tests during many tests involving running the motors during Jan-March 2000. Especially to the point are the tests of the shock absorbers (2. below) when we deliberately stalled the telescope and the drives did not slip. This is a test designed to detect the gross slippage that might occur if the telescope binds up with the drive wheels spinning, as opposed to the small amounts of slippage that could occur if the telescope changes direction rapidly at high speed. The latter is measured in test 2.1.1 below.
TSU with the advice and assistance of MSFC shall conduct a null test of the primary mirror to verify the function of the lateral-support system for the 2-m primary mirror. This test shall be done with the mirror supported vertically in its cell. MSFC will advise on any readjustment of the support system required and shall be responsible for interpreting the test and deciding whether the lateral support system is ready for shipment. Inasmuch as two competent optical engineers agree that the figure of the mirror would not have changed since its manufacture, no other optical tests of the primary shall be required of it. The secondary mirror shall be tested by observing stars in Arizona.
These tests were scheduled for 30 March 2000 and 4 April, to be run by Ron Eng et al. from Marshall. The results of these tests were inconclusive; the test was difficult to set up in the field with the equipment at hand, the telescope did not focus with the null lens available, and MSFC has never made a successful null lens with the techniques they used for this one. On the other hand, MSFC performed some Ronci tests that showed there were no major distortions of the mirror, and the field test conducted by Robert Parks on this mirror when he was configuring it for a lidar system gave images as good as were expected from the interferograms obtained during its manufacture.
TSU shall run the telescope under computer control in the assembly building at rates simulating the range of motions required, specifically at 10 steps/s (appx 2 arcsec/s), 200 steps/s (siderial rate), 2500 steps/s for azimuth (largest tracking rate through meridian), and 70,000 steps/s (slewing rate). These rates will be used to verify or assess the following criteria.
These tests are done as of 5 March 2000. We ran the tests given in the following tables for azimuth and zenith distance. The numbers given are how much an encoder position changed, in inches, after we drove the telescope off by a certain angle then drove it back. The scale is of the order of 5 arcsec per 0.001 inches, with an uncertainty caused by resetting the encoder differently of about 0.0005 inches (2-3 arcsec). There was obviously very little slippage at driving speeds (which would be those used for tracking stars and offsetting from one star to another, and the drives clearly pass that test, even though we made the criterion unreasonably tight. The slippage far larger slews, however, was somewhat more pronounced and may require working around roughly 1-arcmin errors in positions after slews. Marshall conducted similar, although less precise tests (precision of an arcmin) of the drives and found similar results.
This test is an ill advised version of the repetition tests above. We have run enough tests with the home switches to know that they repeat (i.e., have a setting error) of the order of 1-2 arcsec as detailed below.
We have started running this test with the Galil controller during the week of 20 March, 2000, since it was not technically feasible before then (with the NextMove control board). The first sets of data show a difference between the two tilt encoders of about 1 arcmin, mostly from a difference in roller diameter (presumably correctable with a suitable calibration). The differences among the four encoders in azimuth were greater, again reflecting a difference in roller diameter as well as the known runout of the azimith drive wheel. We have further tests planned for the following week to test for repeatability of the patterns detected.
We wired these switches into the control system and tested them on 14 March 2000.
We ran the telescope into the shock absorbers at slewing speed on 10 March 2000, and the shocks stopped the telescope smoothly. We were then able to restart the drives after these tests without maintemance of the telescope except to reset the azimuth shocks (which do not have a return spring).
We wired these devices into the control system and tested them on 15 March 2000. They seemed to have a random setting error of 13 encoder counts, appx 1.3 arcsec.
TSU shall wire up all lines for bringing AC power into the telescope prior to tests in II.A. These will be in a two-part umbilical that is to be secured at the top of the fork and at its outlet in the base. TSU shall verify that the ends of these wires are long enough to reach a distribution box on the south wall of the telescope enclosure. Also, the auxiliary DC power supplies shall be wired into the control box on the telescope.
The power lines were wired in as of 1 January 2000. The DC power supplies were in place as of 13 March 2000.
TSU shall hook up all the wires necessary to run the telescope's basic motions as part of tests 2.1 above.
The wires for testing the motion control system have essentially been in place since January 2000.
These harnesses shall be finished and fitted into the telescope prior to shipping; the placement and function of all holes through which they pass shall be verified.
These wires are fitted into the telescope structure and are sized for fitting into the telescope once the parts are fully tested and taken to the observatory. We will take the parts of these cables that go with the telescope and keep the parts (ends with multiple connections to the motor controllers) that are necessary for testing the devices, such as the instrument head, that we are not taking to the observatory with the telescope.
On completing these tests, TSU shall present a report to the Withbroe committee certifying that the telescope conforms to the stated criteria. Upon completion of this report, the telescope may be shipped to its site at the discretion of TSU.