TSU 2-m AUTOMATIC SPECTROSCOPIC TELESCOPE PROJECT Monthly Report for February, 2000 This monthly report for the TSU 2-m AST project covers the calendar month of February, 2000. The first part of the report (I) discusses what we did with the expected highlights identified in last month's report; the second section (II--VIII) covers the status of various tasks in the schedule; and a third part (IX) gives expected highlights for March. During February, 2000, we continued to have one part- time employee (Mike Williamson) working at TSU on the telescope program, in computer programming and electronic instrumentation, in addition to M. Krebs and M. Wells, who provide machining work at their private shops. Undergraduate student Kenneth McDavis continued doing a project related to the control system. I. HIGHLIGHTS FOR THE PAST MONTH During February, 2000, we said we expected to do the following things [with steps taken then in brackets]: (1) to run MSFC's test of the lateral mirror support system (Task 119), [This is further delayed to give MSFC time to get optical parts and instruments to run the test. We hope it happens soon.] (2) to run further slippage tests on the altitude and azimuth drive tractors, [These are now finished. We ran two types of slippage tests, one in which the telescope drives (slews) off a certain distance then comes back to its original position, and one in which we drive it with a small sinusoidal velocity and watch it reverse direction. The former showed a slight amount of slippage in long slews (of the order of 20 arcsec in some cases) but none to within the errors of measurement for shorter or slower displacements. The sinusoidal test showed no hysteresis in the drive.] (3) to finish adjusting and pinning the top end (Task 106), [We finished this task by pinning two of the feet, by reaming the attachment holes for all four feet, and by making a jig for aligning the axis of the tube to within an arcmin of perpendicular to the tilt axis when we set the telescope up in Arizona.] (4) to finish testing the basic motions in azimuth and Zenith distance (Task 168, extended). [We have been running the telescope at least three times a week throughout February to look for mechanical startup problems related to function of the oil bearings and drives.] (5) to decide what computers to use for telescope control and control of the CCD in the spectrograph and start procuring them (Tasks 147 and 174),[We contacted Andre Hedrick for advice about the computer for the telescope on 7 Feb. As of the end of February, he is still working on the problem. For Task 174, the computer for the spectrograph, we have decided to use a Sun Ultra 5, on the advice of Bob Leach, and Leach is buying it for us through an extension of our contract with him.] (6) to continue integrating and testing the Panasonic guide camera in the acquisition/guiding head, and to make enough observations of stars with the camera to assess a limiting magnitude for acquisition and guiding (part of Task 175) [Williamson obtained images of a starfield with a range of exposures (1/30 sec to 5 min) with the guide camera. Geoff Hall will analyze them for us in March with IRAF to determine the limiting magnitude and assess the noise expected.] (7) to conduct mechanical tests of the secondary-mirror cell (Task 239) [We finished anodizing the remaining parts of the cell during the week of 14 Feb, ihave been slowly reassembling the cell since, but must defer testing it until we get some further modifications made to the spider holding up the mirror.] (8) to decide how to proceed with procurement of the spectrograph camera. [We sent off the report from Harland Epps to Peter Maymon for checking. He is getting one of his engineers to vet the design, and we expect to hear from him in March. Tentatively, we have decided to build the 500-mm camera discussed in last month's report and are commissioning Harland Epps to draw up bidding documents for procuring the glass for the lenses.] II. ADMINISTRATION During February Eaton made a fact-finding trip to Arizona (Task 34). He visited Fairborn Observatory on 11 Feb to confer with Lou Boyd about the readiness of the enclosures to receive the 2m telescope. The enclosure is ready to receive the telescope and to conduct initial tests on the telescope. In particular, the floor is painted and cured. Eaton also visited Sierrita Mining, the contractor Fairborn will use to put the telescope in place, to verify that their equipment is adequate for handling and installing the telescope. Eaton and Boyd agreed on the final wiring for the enclosure and for control of the building's motions. Eaton also visited the SOAR project and discussed control systems with Gerald Cecil, the Spacewatch project to check on its status, with a consulting engineer that we might hire to solve mechanical problems if needed, and with Don Epand to discuss some questions about the control system. Also, during this time, we wrote a renewal proposal for the CASS center. III. FINISH ENCLOSURES Task 51: Build building controls: Boyd and Eaton agreed that the air motor they had intended to use to move the top half of the building on its tracks will not produce enough torque at low speed and decided to replace it with a DC motor with AC controller, which Boyd will acquire. The air motor would have required two auxillary tanks, which we did not yet have, and it would have performed poorly when the roof was stalled, such as in high wind. The existing compressor/tank will now be adequate for running the pneumatic controls for the enclosure's front door. Task 60: Wiring in telescope enclosure: Boyd and Eaton decided what circuits are needed and how to wire them. Task 63: Modify Building for spectrograph and controls: We finished a preliminary design of the insulation of this building and placement of the spectrograph in it. IV. MECHANICAL INTEGRATION Tasks 75&95: Assembly of telescope: This task is now complete. We ran acceptance tests I.A.1 on 8 Feb and 15-29 February. V. CCD DETECTOR AND ITS CONTROLLER Our contract with San Diego State is proceeding apace with delivery of the CCD system expected in April. We will buy the Sun computer for controlling this system through SDSU. VI. CONTROL SYSTEM Williamson has been integrating the motion-control algorithm into the program that calculates position on the sky. These programs now will run the two axes of the simulator. We expect them to be ready to run the telescope once it is relocated to Arizona. In late February, Williamson began thinking about integrating the communications between computers (through an internet socket) into these programs. At present, this code exists as separate programs that run the stepper motors over an internet connection and pipes. He is developing the telescope-control program on a single computer, sending commands to the telescope-control daemon from a front program through named pipes (cf. ast-13-a02). Boyd and Epand have made progress on running the Panasonic guide camera in the other telescopes they are building for us. Boyd had written a program to control it under linux almost exactly the same as the one Williamson wrote independently here. Epand is writing a somewhat slicker program that should be directly applicable to the 2-m telescope. During his visit to Arizona, Eaton discussed control systems with Gerald Cecil of the SOAR project. The purpose of this talk was to determine how SOAR is using LabView, a program the hectoring Dr. Gull is so enthusiastic about. These talks confirmed Eaton's understanding that LabView is like an operating system running on top of the computer's normal operating system. It has the advantage of making it possible to set up communications between processes and different computers relatively easily. However, it requires that many of the application programs for telescope control be written graphically, which is foreign to Fairborn Observatory. SOAR has an expert on writing these graphical programs that are its idiom, while we have experts in writing C programs under linux. Also, SOAR has black-box programs to do the motion control (the programs Eaton, Hedrick, and Williamson have been writing for the last several months) that LabView can communicate with. Commersial software, such as LabView, would thus not have relieved us of the task of writing this kind of very device-dependent software. One interesting side line of this discussion is that National Instruments has started writing linux drivers for its devices, a potential benefit independent of LabView. Student McDavis continues working on his project to study the availability of guide stars in random fields around the sky, although he has been slowed by a senior project he is doing in the engineering school. VII. SPECTROGRAPH CAMERA Tasks 187-191: We have finished the preliminary design of the spectrograph, reviewed it internally, and sent it off to Peter Maymon for his review. Task 210: Design mounts for optical elements: We have preliminary designs for mounts for the echelle grating, cross-dispersion grating, and the two reimaging mirrors based on modifications of designs we got from R. Tull at Texas. VIII. CALIBRATION SYSTEM Tasks 255-257: Assembly/modification of the guiding head: We took the guiding head apart, had the aluminum parts anodized, and reassembled the guiding head. During the time it was disassembled, we cut holes in the base for various cables and added mounts for the stepper- motor control boards. We have reassembled it in late February. The guiding head is now as finished as it will be before we integrate it with the fiber feeds and calibration bench. Tasks 263: Acquire fibers. We received the three 12-meter fiber patch cords from Thor Labs that will let us construct prototype data fibers for the instrument. Tasks 267-269: Calibration bench: We have received most of the parts for building the calibration system and started assembling them. We have a design for all of this device except for the limit switches and hard stops for a flip mirror. We expect to receive the remaining parts for this assembly during March. Parts still missing at this time are the power supplies for the light sources, the hollow-cathode lamp for wavelength calibration, and a couple of mechanical parts for the bench. During February we constructed the flip mirror for switching between the two light sources. IX. HIGHLIGHTS FOR THE NEXT MONTH During March, 2000, we expect (1) to finish all the mechanical acceptance tests for the telescope, (2) to begin making modifications of the oil bearings, (3) to acquire the actual computers to run the telescope (Task 174), (4) to arrange to take delivery of the CCD dewar and controller in late March or early April (Tasks 145-150), (5) to finish the calibration bench and start integrating it with the guiding head, and (6) to begin procuring the spectrograph camera.