TSU 2-m AUTOMATIC SPECTROSCOPIC TELESCOPE PROJECT Monthly Report for June, 2000 This monthly report for the TSU 2-m AST project, now liberated from the hubris of NASA Code S, covers the calendar month of June, 2000. The first part of the report (I) discusses what we did with the expected highlights identified in last month's report; the second section (II--VII) covers the status of various tasks in the schedule; and a third part (VIII) gives highlights for July. During June, 2000, we continued to have one part-time employee (Mike Williamson) working at TSU on the telescope program, in computer programming and electronic instrumentation, in addition to M. Krebs and M. Wells, who provide machining work at their private shops. Allen Keel continued doing projects related to the control system as a summer student. I. HIGHLIGHTS FOR THE PAST MONTH During June, 2000, we said we expected to do the following things [with steps taken then in brackets]: (1) to transport the telescope to Arizona, [We loaded the telescope onto two flatbed trucks from sierrita Mining on 7 June and unloaded it at Fairborn Observatory on 12 June. Eaton, Williamson, Boyd, and various contract workers from Sierrita spent the next seven days assembling the telescope and conducting preliminary tests on it. The telescope suffered essentially no damage in transit, the only damage being water damage from the month NASA delayed shipment. The telescope was performing all the tasks it had in the assembly building in Nashville, at least as well.] (2) to continue writing the telescope control software, specifically preparing it for supporting Tasks 172, 175, and 177, [Williamson has continued writing these programs and they will be ready to use for our next trip to work on the telescope in July.] (3) to arrange with Bob Leach for actual delivery of the CCD dewar and controller (Tasks 145-150), [Delivery has been delayed by a misunderstanding about what CCD we actually have, but it is expected for July.] (4) to finish the paperwork for procuring the material and services for constructing the camera for the spectrograph, [Busby iand Epps have made significant progress on these tasks, with sole-source contracts for the calcium-fluoride and glass lens blanks and for the cell design, with a contract for the lens generation (polishing) and with bidding for lens coating.] (5) to finish contracting with Jeff Hall to write the data reduction and handling system. [This task is finished.] II. ENCLOSURES Boyd has wired up the enclosures and finished the building control enough that we can run the top with a hand controller and the front door with a push-button pneumatic switch. These properties were quite adequate for assembling the telescope and will be sufficient for the first round of testing the telescope in the two or three months to come. He has done almost all of the routing of electrical cables in the main telescope enclosures, including installing work lights, but has deferred wiring the control buildings until they are modified and insulated by Sierrita. We have finished discussions with Sierrita Mining about how to modify those two buildings for the spectrograph and control room and expect to finish that work this summer. V. SET TELESCOPE UP AT SITE We accomplished this task over the seven days, June 13-19, 2000. VI. CONTROL SYSTEM Williamson ran the computer under its control system during setup in Arizona, which worked, but detailed tests of the controls must wait until our trip to the observatory in July. VII. SPECTROGRAPH CAMERA Having contracted with Harland Epps to oversee development of the spectrograph camera, we have continued procuring the parts and services for it with his help and supervision. Busby has spearheaded this effort. Using the bidding documents Epps drew up, we have established contracts for obtaining materials for the lenses (CaF2 and optical glass blanksr), which are proceeding, for design of the cell to hold the lenses, and for grinding and polishing the lenses. The contract for coating the lenses to minimize is being rebid but is expected to be resolved by the end of the month. Task 208-210: Mark Wells has made significant progress on manufacturing these mounts and expects to have most of the initial work on them done by the end of July. We have had Marlyn Krebs make some of the smaller parts in Nashville, and these are finished. We still have to produce shop drawings for the device to position the fibers at the focus of the collimator. VIII. HIGHLIGHTS FOR THE NEXT MONTH During July, 2000, we expect to begin detailed testing of the telescope and its control system on site in Arizona, specifically (1) to colimate the primary mirror and achieve first light with it, (2) to obtain images of the north star sufficient to begin testing the optical figure of the primary mirror and assess how well its supports work, (3) to find stars with the evolving control system and perform the first tracking tests with the telescope, (4) to assess the degree to which the telescope mount deviates from alignment in terms of perpendicularity of its axes, (5) to identify students to make mathematical models of the secondary-mirror cell and telescope mount and devise algorithms for moving the secondary with its drive motors and for correcting pointing for imperfections in the mount, (6) to continue procuring the material and services for constructing the camera for the spectrograph with the aid of Harland Epps.