TSU 2-m AUTOMATIC SPECTROSCOPIC TELESCOPE PROJECT Monthly Report for March, 2001 This monthly report for the TSU 2-m AST project, now liberated from the hubris of NASA Code S, covers the calendar month of March, 2001. The first part of the report (I) discusses what we did with the expected highlights identified in last month's report; the second section (II-III) covers the status of various tasks in the schedule; and a third part (IV) gives highlights for February. During January, 2001, we continued to have one part-time employee (Mike Williamson) working at TSU on the telescope program, in computer programming and electronic instrumentation, in addition to M. Krebs and M. Wells, who provide machining work at their private shops. Sean Willaims, a graduate student in electrical engineering, joined the group to work on the CCD controller for the spectrograph. We had intended to take the secondary mirror to Arizona in January, but it was still not back from refiguring, so we spent our work session of 24-29 March working on the control system and fitting the telescope enclosure with interlocks to prevent damage to the telescope. I. HIGHLIGHTS FOR THE PAST MONTH During March, 2001, we said we expect to do the following things, most of which have to do with testing the telescope in Arizona [with steps taken on them in brackets]. (1) to put the secondary mirror into the telescope and get it to focus, [We could not do this because because Torus Optics still was unable to deliver the mirror after having back in their shop for testing and refiguring since May, 2000.] (2) to run extensive tests on the telescope with the secondary in place, (Some of these are pointing tests, focusing tests, imaging tests of the quality of the overall optical system, and tests to determine how difficult it will be to guide on light spilling over the sides of the optical fiber.), [Deferred; no secondary mirror] (3) to finish a number of small tasks at the observatory related to tying up loose ends, [We made progress on these, but there are still things to do over the next couple of months.] (4) to integrate into the control system limit switches to monitor the position of the movable parts of the enclosure and to determine when the telescope is at its home position, [We did this on our trip to the observatory.] (5) to tie up some loose ends on the oil-pumping system such as rewiring the primary pumps for 220V and tidying up the secondary return system, [We finished these tasks.] (6) to continue assembling the mounts for the spectrograph optics, integrating the optical elements into them, and designing and building the system for getting light into the spectrograph, [We made some progress on these jobs. The main tasks remaining are putting the echelle grating into its mount, gluing the pucks onto it, finishing the fiber feed into the spectrograph (which exists in a number of parts that require some modifications), and procuring the flat reimaging mirror and coating the various mirrors.] (7) to continue exercising the CCD controller, [We did some of this, but it was a low priority in March.] and (7) to continue procuring the material and services for constructing the camera for the spectrograph with the aid of Harland Epps, [We didn't do very much in this area other than sending the lens blanks to the optical shop. II. ENCLOSURES We discussed with Lou Boyd the details of how to automatge the motions of the telescope enclosure and a schedule for doing it. The building should be ready for tests of automatic operation of the telescope before the summer shutdown this year. III. CONTROL SYSTEM Williamson continues to make progress on writing the control system for running the telescope. This month he ran further tests to verify new routines for moving the secondary mirror and instrument head, for turning on the oil pump and reading its status, and for reading the status of the enclosure before a slew and responding to it. We also modified the executive program that decides what star to observe so as to run through a list of stars, acquire them automatically, and track them for five minutes while recording statistics about the quality of tracking. These tests, which we ran on three nights, worked flawlessly--for a span of about four hours on each night. They went so well that we should be able to start running the telescope remotely, if not automatically, once the controls for the roof of the enclosure are finished. IV. HIGHLIGHTS FOR THE NEXT MONTH During April, 2001, we expect to take the instrument head, the secondary mirror and its cell, and many of the spare parts to the observatory. Specifically, we expect (1) to make a decision on how to deal with Torus Optics and their seeming inability to finish refiguring our secondary mirror, (2) if possible, to put the secondary mirror into the telescope and get it to focus, (3) to run extensive tests on the telescope with the secondary in place, (Some of these are pointing tests, focusing tests, imaging tests of the quality of the overall optical system, and tests to determine how difficult it will be to guide on light spilling over the sides of the optical fiber.), (4) to straighten up the wiring in the observatory and to get the computers for the AST switched over to the new Internet connection, (5) to continue assembling the mounts for the spectrograph optics, integrating the optical elements into them, and designing and building the system for getting light into the spectrograph, (6) to continue exercising the CCD controller for the spectrograph, and (7) to continue procuring the material and services for constructing the camera for the spectrograph with the aid of Harland Epps.