TSU 2-m AUTOMATIC SPECTROSCOPIC TELESCOPE PROJECT Monthly Report for October, 2000 This monthly report for the TSU 2-m AST project, now liberated from the hubris of NASA Code S, covers the calendar month of October, 2000. The first part of the report (I) discusses what we did with the expected highlights identified in last month's report; the second section (II-III) covers the status of various tasks in the schedule; and a third part (IV) gives highlights for October. During October, 2000, we continued to have one part-time employee (Mike Williamson) working at TSU on the telescope program, in computer programming and electronic instrumentation, in addition to M. Krebs and M. Wells, who provide machining work at their private shops. Williamson and Eaton made a trip to Arizona to work on the telescope, and Roy Young from Huntsville, Alabama (NASA-MSFC) joined them for the last three days of the session. The weather there was abnormally wet, which made observing impossible on all but two-three nights and difficult on all but one night. I. HIGHLIGHTS FOR THE PAST MONTH During October, 2000, we said we expected to do the following things, most of which had to do with resuming testing the telescope on site [with steps taken on them in brackets]: (1) to move the control console for our tests into the control building and use it for conducting further tests of the control system, [We decided not to do this in October because we did not have cables long enough to run to the video monitors. We did fish a temporary cable for protected power through the holes into the control building, and we ran further acquisition and tracking tests.] (2) to recolimate the primary mirror by using the comatic shapes of off-axis star images, [We did this and got the optical axis alighed to the physical axis to within about 0.5 arcmin.] (3) to make more critical observations of stars to verify the mirror-support system and assess the image quality of the primary mirror, [We took two sets of images inside and outside focus, as well as several images of faint stars at close to optimal focus. The extrafocal images show there is probably a slight, but small amount of spherical aberration but little in the way of other problems. The focused images show spreads of about two pixels, roughly 1.6 arcsec. This image size is entirely consistent with measurements made in an earlier incarnation of the mirror by R. Parks, our optical consultant.] (4) to implement the mount model in the telescope control system and retest the pointing and tracking of the telescope, [We did this on one night and part of another, although the weather was awful for much of our October work session.] (5) to make a number of minor mechanical and electrical modifications of the telescope hardware designed to make the telescope more reliable, [We painted some rusting metal on the telescope, fitted the base skirt, cleaned up the enclosure, and fitted a temperature/humidity sensor into the control system.] (6) possibly to put the secondary mirror into the telescope, along with the guiding head, and use it to run the first tests of the telescope as a Cassegrain system, [This task is deferred indefinitely until we can get the secondary mirror back from the optical shop, where it's being refigured.] (7) to finish assembling the mounts for the spectrograph optics and finish a preliminary design of the fiber feed for the spectrograph, [We have continued assembling these mounts and modifying them to take the optical components. The mounts for the two gratings and collimating/re- imaging mirrors should be finished by the end of December. The ones for the mirrors lack holes for attaching the pucks in the back plates and some modifications to various small parts. The stands for the gratings lack several small modifications and final assembly. The stand for the echelle grating lacks attachment points machined into it for the fiber feed and reimaging mirror. Most of the parts of these stands still have to be anodized. On the other hand, we have nearly finished designing the fiber feeds and the reimaging mirror and its mount.] (8) to take delivery of the CCD controller for the spectrograph from SDSU, [We had to order the computer for this system through TSU after SDSU could not do it for us, and this is delaying delivery of the electronics to control the CCD further. The computer is supposed to arrive in November (17th), so the CCD control system should be finished some time in December.] and (9) to continue procuring the material and services for constructing the camera for the spectrograph with the aid of Harland Epps. [This task is proceeding on schedule with delivery of most of the glass expected in November.] II. ENCLOSURES We extended our contract with Sierrita Mining to furnish a storage building at the site to hold the box for the primary mirror, the pallets for the fork and top-end structure, and various test and assembly equipment too large to store in the telescope enclosure or control room. We have arranged the furniture in the control room and nearly finished getting all the superfluous equipment out of the telescope enclosure. Boyd has made progress on getting the AST hooked up to the Internet. III. CONTROL SYSTEM Williamson continues to make progress on writing the control system for running the telescope. He has now integrated the mount model into the control program, and added sensors to measure temperature, humidity, and atmospheric pressure, and started designing the routines to control the secondary mirror and instrument head. IV. HIGHLIGHTS FOR THE NEXT MONTH During November, 2000, we expect to prepare for another work session at the observatory in early December to continue detailed testing of the telescope and its control system and to continue progress on the echelle spectrograph. Specifically, we expect (1) to modify the telescope's base skirt to provide an access hole through it and to cut it off to a uniform height that will not rub the base, (2) to obtain everything we need to move the control console for tests into the control building, (3) to obtain material for finishing the secondary oil-return system (now manual, via a pan), for putting louvers into the pump house, for finishing the air sucker for the telescope and to send all this stuff out to Fairborn Observatory, (4) to finish fitting together and testing the secondary mirror cell and instrument head as systems and decide how to get them out to the observatory, (5) with the help of NASA MSFC, to continue bugging Torus Optics to finish refiguring the secondary mirror, (6) to continue assembling the mounts for the spectrograph optics and design the jigs for assembling the components in them, (7) to take delivery of the computer for the CCD controller for the spectrograph and send it to SDSU, and (8) to continue procuring the material and services for constructing the camera for the spectrograph with the aid of Harland Epps.