TSU 2-m AST Task List


Project Start Date: Tue 6/1/99
Project Finish Date: Thu 4/12/01

IDNameDurationStart_DateFinish_DatePredecessorsResource_Names
1      
2
OVERHEAD
481 daysFri 5/28/99Fri 3/30/01  
3
Writing reports
300 daysTue 6/1/99Mon 7/24/00 JAE[1%]
4
Monthly reports
436 daysFri 7/30/99Fri 3/30/01  
5
Monthly reports 1
1 dayFri 7/30/99Fri 7/30/99  
6
Monthly reports 2
1 dayFri 8/27/99Fri 8/27/99  
7
Monthly reports 3
1 dayFri 9/24/99Fri 9/24/99  
8
Monthly reports 4
1 dayFri 10/29/99Fri 10/29/99  
9
Monthly reports 5
1 dayFri 11/26/99Fri 11/26/99  
10
Monthly reports 6
1 dayFri 12/31/99Fri 12/31/99  
11
Monthly reports 7
1 dayFri 1/28/00Fri 1/28/00  
12
Monthly reports 8
1 dayFri 2/25/00Fri 2/25/00  
13
Monthly reports 9
1 dayFri 3/31/00Fri 3/31/00  
14
Monthly reports 10
1 dayFri 4/28/00Fri 4/28/00  
15
Monthly reports 11
1 dayFri 5/26/00Fri 5/26/00  
16
Monthly reports 12
1 dayFri 6/30/00Fri 6/30/00  
17
Monthly reports 13
1 dayFri 7/28/00Fri 7/28/00  
18
Monthly reports 14
1 dayFri 8/25/00Fri 8/25/00  
19
Monthly reports 15
1 dayFri 9/29/00Fri 9/29/00  
20
Monthly reports 16
1 dayFri 10/27/00Fri 10/27/00  
21
Monthly reports 17
1 dayFri 11/24/00Fri 11/24/00  
22
Monthly reports 18
1 dayFri 12/29/00Fri 12/29/00  
23
Monthly reports 19
1 dayFri 1/26/01Fri 1/26/01  
24
Monthly reports 20
1 dayFri 2/23/01Fri 2/23/01  
25
Monthly reports 21
1 dayFri 3/30/01Fri 3/30/01  
26
June 1999 review
1 dayTue 6/29/99Tue 6/29/99 JAE[50%],MRB[50%]
27
Write reports
15 daysTue 6/8/99Tue 6/29/9926SFJAE[25%],MRB[25%]
28
Hiring technicians
20 daysMon 7/5/99Fri 7/30/99 JAE[6%],MRB[6%]
29
Hiring instrumentalist/programmer
40 daysMon 7/5/99Fri 8/27/99 JAE[3%],MRB[3%]
30
Assess spare parts
20 daysMon 8/2/99Fri 8/27/99 JAE[3%],MRB[3%]
31
Travel for JAE
221 daysFri 5/28/99Fri 3/31/00  
32
Trip to California
3 daysFri 5/28/99Tue 6/1/99 JAE
33
July vacation
1 dayFri 7/9/99Fri 7/9/99 JAE
34
Trip to Arizona
5 daysMon 8/16/99Fri 8/20/99 JAE
35
January vacation
5 daysMon 1/3/00Fri 1/7/00 JAE
36
Telescopes conference?
5 daysMon 3/27/00Fri 3/31/00 JAE
37
Relocate telescope to Franklin
42 daysThu 6/17/99Fri 8/13/99  
38
Take telescope apart
3 daysMon 7/5/99Wed 7/7/99 JAE[50%],MT[50%]
39
Put on pads
8 daysThu 7/8/99Mon 7/19/9938JAE[50%],MT[50%]
40
Add guards to parts
2 daysTue 7/20/99Wed 7/21/9939JAE[33%]
41
Transport to Armory
5 daysThu 7/22/99Wed 7/28/9940Continential
42
Contract for moving
10 daysThu 6/17/99Thu 7/1/9941SF-15 daysMRB[5%]
43
Contract for space
10 daysThu 6/17/99Thu 7/1/9941SF-15 daysMRB[5%]
44
Telescope relocated
0 daysWed 7/28/99Wed 7/28/9941 
45
Set up telescope base
10 daysMon 8/2/99Fri 8/13/9944FS+2 daysJAE[20%],MT[20%]
46
Arrange electric service
10 daysMon 7/5/99Mon 7/19/9945SF-10 daysMRB[5%]
47
Begin operations
0 daysThu 3/1/01Thu 3/1/01216 
48      
49
FINISH ENCLOSURES
240 daysTue 6/1/99Mon 5/1/00  
50
Design building control
30 daysThu 7/1/99Wed 8/11/99 LJB[10%]
51
Build building control
30 daysThu 8/12/99Wed 9/22/9950LJB[10%]
52
Paint concrete floors
30 daysTue 6/15/99Mon 7/26/99 LJB[10%],contractor
53
Cure paint before using
30 daysTue 7/27/99Mon 9/6/9952 
54
Enclosure ready for telescope
0 daysMon 9/6/99Mon 9/6/9953 
55
UPS/Wiring
65 daysTue 6/1/99Mon 8/30/99  
56
Accept bid for UPS
1 dayTue 6/1/99Tue 6/1/99 JAE[5%],MRB[5%]
57
Arrange delivery
40 daysWed 6/2/99Tue 7/27/9956MRB[5%],SM[6%]
58
Get UPS to site
10 daysWed 7/28/99Tue 8/10/9957LJB[5%],SM[20%]
59
Contact Sierrita
20 daysWed 6/30/99Wed 7/28/9958SFMRB[3%]
60
Wiring in building
14 daysWed 8/11/99Mon 8/30/9958LJB[10%],electrician[25%]
61
Enclosure ready for tests
0 daysMon 8/30/99Mon 8/30/9960 
62
Modify/Insulate control buildings
65 daysTue 2/1/00Mon 5/1/00  
63
Design
20 daysTue 2/1/00Mon 2/28/00 JAE[2%],LJB[6%]
64
Glue in place
20 daysTue 3/28/00Mon 4/24/0063FS+20 daysLJB[5%],SM[25%]
65
Insulation contract
30 daysTue 2/15/00Tue 3/28/0064SFMRB[2%],JAE[2%]
66
Place air conditioners&ducts
3 daysTue 4/25/00Thu 4/27/0064LJB[5%],SM[25%]
67
Wire in air conditioner
2 daysFri 4/28/00Mon 5/1/0066LJB[33%],electrician
68
Ready for spectrograph
0 daysMon 5/1/00Mon 5/1/0067 
69      
70
FINISH MECHANICAL INTEGRATION
113 daysWed 6/2/99Fri 11/5/99  
71
Assemble drive tractors
2 daysWed 6/2/99Thu 6/3/99 JAE[33%]
72
Put drive tractors in telescope
2 daysFri 6/4/99Mon 6/7/9971JAE[25%]
73
Adjust clamps and hardware
15 daysTue 6/8/99Mon 6/28/9972JAE[12%]
74
Modify fittings
5 daysThu 7/8/99Wed 7/14/9973FS+7 daysMEK[12%]
75
Finish adjusting clamps
5 daysMon 8/23/99Fri 8/27/9974,45FS+5 daysJAE[25%]
76
Make cables for amplifiers
5 daysFri 6/4/99Thu 6/10/9971AH[25%]
77
Contingency for modifying attachments
60 daysMon 8/16/99Fri 11/5/9945JAE[1%],MEK[6%]
78
Make jig for gluing puck
2 daysWed 6/2/99Thu 6/3/99 JAE[12%]
79
Glue hard-pt puck back on
4 daysFri 6/4/99Wed 6/9/9978JAE[6%]
80
Attach hard points
4.5 daysThu 6/10/99Wed 6/16/9979JAE[8%]
81
Finish attachments for lat supp
12 daysWed 6/16/99Fri 7/2/9980MEK[10%]
82
Integrate base skirt
3 daysTue 6/29/99Thu 7/1/9973SS+10 daysJAE[25%]
83
Insulate exposed surfaces
40 daysWed 6/30/99Tue 8/24/99 JAE[1%],KMD[3%],MT[1%]
84
Construct wiring harnesses
40 daysWed 6/30/99Tue 8/24/99 MT[12%],JAE[12%]
85
Buy cables and connectors
5 daysWed 6/23/99Wed 6/30/9984SFAH[10%],JAE[10%]
86
Make power cables
2 daysMon 8/16/99Tue 8/17/9985,45JAE[25%]
87
Set ampl. In torque mode
2 daysWed 8/18/99Thu 8/19/9986MT[12%]
88
Put amplifiers into telescope
1 dayFri 8/20/99Fri 8/20/9987JAE[12%],MT[25%]
89
Test amplifiers for motion
2 daysThu 9/30/99Fri 10/1/9988,95JAE[25%]
90
Decide on anodizing sector
5 daysWed 6/23/99Tue 6/29/99 JAE[6%]
91
Find shop to anodize
3 daysWed 6/30/99Fri 7/2/9990JAE[12%]
92
Run test piece
5 daysMon 7/5/99Fri 7/9/9991JAE[3%]
93
Transport sector
2 daysTue 7/20/99Wed 7/21/9939,92 
94
Get sector anodized
30 daysThu 7/22/99Wed 9/1/9993Outside shop
95
Finish assembling telescope
20 daysThu 9/2/99Wed 9/29/9994JAE[20%],MT[20%]
96
Mech. Int.done
0 daysWed 9/29/99Wed 9/29/9995 
97
Redesign axial supports
1 dayThu 7/1/99Thu 7/1/99 JAE[12%],MEK[12%]
98
Purchase material
2 daysFri 7/2/99Mon 7/5/9997JAE[12%],GD[12%]
99
Finish modification
5 daysTue 7/6/99Mon 7/12/9998MEK[25%]
100
Add aux. Oil return system
4 daysThu 7/29/99Tue 8/3/9941JAE[50%]
101
Wire up oil-pump control
2 daysTue 7/27/99Thu 7/29/99100SFJAE[12%],MT[12%]
102
Test aux oil return syst
4 daysWed 8/4/99Mon 8/9/99100JAE[50%]
103
Buy plastic slugs
3 daysTue 7/27/99Fri 7/30/99102SF-3 daysJAE[6%]
104
Contingency (oil ret)
10 daysTue 8/10/99Mon 8/23/99102JAE[12%]
105
Cut clearances in parts
2 daysThu 7/29/99Fri 7/30/9941JAE[25%],MEK[25%]
106
Center top end
3 daysMon 8/2/99Wed 8/4/99105JAE[25%],KMD[25%]
107
Finish mirror-washing dam
4 daysThu 7/29/99Tue 8/3/9941JAE[12%]
108
Machine dam fittings
2 daysTue 7/27/99Thu 7/29/99107SFJAE[12%]
109
Boxes for electronics
20 daysMon 8/16/99Fri 9/10/9945JAE[3%],Hamilton?
110
Contract
10 daysMon 8/2/99Mon 8/16/99109SFMRB[3%],JAE[3%]
111
Design boxes
5 daysMon 7/26/99Mon 8/2/99110SFJAE[12%]
112      
113
TEST PRIMARY MIRROR
195 daysWed 6/2/99Tue 2/29/00  
114
Contact optical consultant
3 daysWed 6/2/99Fri 6/4/99 JAE+MRB contact R. Parks
115
Obtain and review report
5 daysMon 6/7/99Fri 6/11/99114RP[10%],JAE[5%]
116
Discuss project with Jim Bilbro
1 dayWed 6/2/99Wed 6/2/99 JAE[25%],MRB[25%]
117
Decide how MSFC can help here
10 daysThu 6/3/99Wed 6/16/99116JAE[10%],MRB[10%]
118
Set up test with Scott Smith
2 daysThu 6/17/99Fri 6/18/99117JAE[10%],MRB[12%]
119
Run test
2 daysThu 9/30/99Fri 10/1/9995JAE[50%],SS[50%]
120
Finish setting up
6 daysWed 9/22/99Thu 9/30/99119SFJAE[12%]
121
Decide how to proceed
10 daysMon 10/4/99Fri 2/25/00119JAE[25%]
122
Write report on results
2 daysMon 2/28/00Tue 2/29/00121JAE[25%]
123
End mirror testing
0 daysTue 2/29/00Tue 2/29/00122 
124
Rough loading calculation
2 daysMon 6/14/99Tue 6/15/99 MW[25%]
125
Calculate effects of support
40 daysThu 7/1/99Wed 8/25/99 AK[25%],JAE[1%]
126
Reauthorize ANSYS
15 daysThu 6/10/99Thu 7/1/99125SFMRB[2%]
127      
128
SET TELESCOPE UP AT SITE
61 daysMon 11/8/99Mon 1/31/00  
129
Take telescope apart
3 daysMon 11/8/99Wed 11/10/9977JAE[50%],MT[50%]
130
Put on pads
4 daysThu 11/11/99Tue 11/16/99129JAE[50%],MT[50%]
131
Contingency for modifications
20 daysWed 11/17/99Tue 12/14/99130JAE[2%]
132
Transport to Arizona
5 daysWed 12/15/99Tue 12/21/99131Continential
133
Establish contract for shipping
20 daysWed 11/17/99Wed 12/15/99132SFMRB[5%]
134
Set up telescope at WC
7 daysWed 1/12/00Thu 1/20/00132FS+7 days,35FS+2 daysJAE[50%],LJB[50%],AH[50%]
135
Travel to Arizona
2 daysMon 1/10/00Wed 1/12/00134SFJAE
136
Arrange staging+ trans to WC
20 daysWed 12/15/99Wed 1/12/00134SFMRB[5%]
137
Contingency
5 daysFri 1/21/00Thu 1/27/00134JAE[50%],LJB[50%],AH[50%]
138
Telescope on site
0 daysThu 1/27/00Thu 1/27/00137 
139
Travel to Nashville
2 daysFri 1/28/00Mon 1/31/00138JAE[50%]
140      
141
GET CCD CONTROLLERS
219 daysTue 7/6/99Fri 5/5/00  
142
Contact SDSU for latest spec
3 daysTue 7/6/99Thu 7/8/99 JAE[10%]
143
Establish contract
60 daysFri 7/23/99Thu 10/14/99142FS+10 daysMRB[3%],JAE[3%]
144
Start controller contract
0 daysThu 10/14/99Thu 10/14/99143 
145
Receive controller
80 daysFri 11/12/99Thu 3/2/00143FS+20 daysJAE[2%]
146
Procure control computer
45 daysFri 9/24/99Thu 11/25/99145SF+10 daysMRB[2%],JAE[2%]
147
Computer contract
30 daysFri 8/13/99Fri 9/24/99146SFMRB[3%],JAE[3%]
148
Training at SDSU
5 daysFri 2/18/00Thu 2/24/00145FF-5 daysJAE[50%],AH[50%]
149
Ship to Nashville
10 daysFri 3/3/00Thu 3/16/00145 
150
Receive controller
0 daysThu 3/16/00Thu 3/16/00149 
151
Test CCD system in lab
30 daysFri 3/17/00Thu 4/27/00149AH[25%],JAE[12%]
152
Integrate into control system
6 daysFri 4/28/00Fri 5/5/00151AH[25%]
153
Ready for data tests
0 daysFri 5/5/00Fri 5/5/00152 
154      
155
WRITE/TEST CONTROL SYSTEM
384 daysWed 6/2/99Mon 11/20/00  
156
Write functions for timing
1 dayWed 6/2/99Wed 6/2/99 JAE+students
157
Write functions for coord conv
1 dayWed 6/2/99Wed 6/2/99 JAE+students
158
Write functions for communication
60 daysThu 6/3/99Wed 8/25/99157JAE[12%],AH[12%]
159
Write basic device drivers
60 daysThu 6/3/99Wed 8/25/99157AH[16%]
160
Implement servo loop
30 daysThu 8/26/99Wed 10/6/99159JAE[12%],AH[12%]
161
Write serial daemons
20 daysSun 8/1/99Fri 8/27/99 JAE[12%]
162
Test with steppers
30 daysMon 8/30/99Fri 10/8/99161JAE[8%]
163
Wire up stepper controllers
30 daysMon 7/19/99Mon 8/30/99162SFJAE[5%],Students
164
Make bases for controllers
5 daysMon 7/12/99Mon 7/19/99163SFJAE[3%],MEK[12%]
165
Acquire stepper controllers
30 daysMon 6/7/99Mon 7/19/99163SFMRB[3%]
166
Test with IO modules
9.86 daysMon 8/30/99Fri 9/10/99161JAE[12%],Mwi[25%]
167
Acquire IO modules
30 daysMon 7/19/99Mon 8/30/99166SFMRB[3%]
168
Tests of basic AZ/ZD motions
15 daysThu 9/30/99Wed 10/20/9995JAE[12%],AH[12%]
169
Test limits, ZP's
10 daysThu 10/21/99Wed 11/3/99168JAE[12%],AH[12%]
170
Basic tests done
0 daysWed 11/3/99Wed 11/3/99169 
171
Set up Apogee cam in lab
20 daysThu 9/2/99Wed 9/29/99159FS+5 daysMwi[25%]
172
Put Apogee cam in tel
20 daysTue 2/29/00Mon 3/27/00139FS+20 daysAH[12%],JAE[12%]
173
Implement control computer
10 daysTue 2/29/00Mon 3/13/00139FS+20 daysAH[12%],JAE[12%]
174
Control-computer contract
30 daysTue 1/18/00Tue 2/29/00173SFMRB[2%],AH[5%],JAE[3%]
175
Begin tracking tests
0 daysMon 3/27/00Mon 3/27/00172 
176
Initial tracking tests
20 daysTue 3/28/00Mon 4/24/00175JAE[12%],AH[12%]
177
Test image quality
20 daysTue 4/25/00Mon 5/22/00176JAE[5%],AH[5%]
178
Verify stepper controls
20 daysTue 4/25/00Mon 5/22/00176JAE[12%],AH[12%]
179
Assess tracking/images
20 daysTue 5/23/00Mon 6/19/00178JAE[25%]
180
Detailed tracking tests
30 daysTue 6/20/00Mon 7/31/00179JAE[12%],AH[12%]
181
Assess guiding strategy
30 daysTue 8/1/00Mon 9/11/00180JAE[25%],AH[25%]
182
Contingency
30 daysTue 9/12/00Mon 10/23/00181JAE[12%],AH[12%]
183
End tracking tests
0 daysMon 10/23/00Mon 10/23/00182 
184
Implement scheduler
20 daysTue 10/24/00Mon 11/20/00183AH[25%],DE[25%]
185      
186
FINISH SPECTROGRAPH
488 daysTue 6/1/99Thu 4/12/01  
187
Have prelim designs of spectrograph
1 dayTue 6/1/99Tue 6/1/99 JAE[50%]
188
Retain optical designer
30 daysWed 6/2/99Tue 7/13/99187MRB[2%],JAE[1%]
189
Begin formal design
0 daysTue 7/13/99Tue 7/13/99188 
190
Prelim design of spect
20 daysWed 7/14/99Tue 8/10/99189DW[25%]
191
Prelim design of camera
32 daysWed 8/11/99Thu 9/23/99190DW[25%]
192
Review results
10 daysFri 9/24/99Thu 10/7/99191DW[12%],JAE[12%]
193
Contingency
20 daysFri 10/8/99Thu 11/4/99192JAE[6%]
194
Have Maymon review
20 daysFri 11/5/99Thu 12/2/99193JAE[10%]
195
Prelim design done
0 daysThu 12/2/99Thu 12/2/99194 
196
Final design of camera
20 daysFri 12/3/99Thu 12/30/99195DW[12%]
197
Contingency
20 daysFri 12/31/99Thu 1/27/00196 
198
Design done
0 daysThu 1/27/00Thu 1/27/00197 
199
Get recommendations for optical shops
10 daysFri 11/5/99Thu 11/18/99193JAE[12%]
200
Lens-cell contract
30 daysFri 11/19/99Thu 12/30/99199MRB[2%],JAE[3%]
201
Design cell for lens
20 daysFri 12/31/99Thu 1/27/00200JAE[12%],DW[12%],contractor[50%]
202
Get lens cell manufactured
60 daysFri 1/28/00Thu 4/20/00201DW[5%]
203
Procure glass blanks for lens
80 daysFri 12/31/99Thu 4/20/00196JAE[5%],MRB[5%]
204
Have lens manufactured
120 daysFri 4/21/00Thu 10/5/00203DW[6%]
205
Lens manufactured
0 daysThu 10/5/00Thu 10/5/00204 
206
Get lenses coated
60 daysFri 10/6/00Thu 12/28/00205DW[6%],JAE[6%]
207
Lens-coating contract
30 daysFri 8/25/00Fri 10/6/00206SFMRB[2%],JAE[3%]
208
Make mounts for optics
30 daysFri 4/21/00Thu 6/1/00203Outside shop
209
Optic-mount contract
30 daysFri 3/10/00Fri 4/21/00208SFMRB[2%],JAE[3%]
210
Design mounts for optics
60 daysFri 12/17/99Fri 3/10/00209SFJAE[3%]
211
Have mirrors coated
60 daysFri 12/31/99Thu 3/23/00196DW[6%],MRB[6%]
212
Mirror-coating contract
12 daysWed 12/15/99Fri 12/31/99211SFMRB[2%],JAE[3%]
213
Begin integration
0 daysThu 12/28/00Thu 12/28/00206 
214
Integrate spectrograph
30 daysFri 12/29/00Thu 2/8/01213JAE[12%],AH[12%]
215
Test spectrograph
15 daysFri 2/9/01Thu 3/1/01214JAE[12%],AH[12%]
216
Spectrogreph done
0 daysThu 3/1/01Thu 3/1/01215 
217
Set up on site
30 daysFri 3/2/01Thu 4/12/01216JAE[12%],LJB[12%]
218      
219
FINISH SMALL SYSTEMS
286 daysTue 6/1/99Tue 7/4/00  
220
Bid + order abs encoders
1 dayWed 6/2/99Wed 6/2/99 MRB[0%]
221
Procure encoders
10 daysThu 6/3/99Wed 6/16/99220MRB[2%]
222
Finish mount for AZ encoder
10 daysTue 6/1/99Mon 6/14/99221MW[84%],MEK[5%]
223
Finish mount for ZD encoder
5 daysTue 6/8/99Mon 6/21/99222MW[25%]
224
Integrate encoders into mounts
6 daysMon 6/21/99Tue 6/29/99223JAE[25%],MW[25%]
225
Make up drive cable
3 daysTue 6/29/99Fri 7/2/99224MW[12%]
226
Modify driven wheel
4 daysFri 7/2/99Thu 7/8/99225JAE[6%],MT[25%]
227
Assemble encoder mounts
4 daysThu 7/8/99Wed 7/14/99226JAE[6%]
228
Contingency
10 daysWed 7/14/99Wed 7/28/99227JAE[3%],MEK[6%]
229
Encoder mounts done
0 daysWed 7/28/99Wed 7/28/99228 
230
Modify sec mirror cell
1 dayWed 6/16/99Wed 6/16/99 MW[25%]
231
Build flexures
2 daysThu 6/17/99Fri 6/18/99230MW[25%]
232
Modify attachments
2 daysMon 6/21/99Tue 6/22/99231MW[25%]
233
Build pulls
5 daysWed 6/23/99Tue 6/29/99232MW[12%]
234
Modify flexures
5 daysWed 6/30/99Tue 7/6/99233JAE[6%],MEK[25%]
235
Add limit switches
5.83 daysWed 7/7/99Wed 7/14/99234JAE[6%],Mwi[12%]
236
Further mod sec cell
15 daysWed 7/14/99Tue 8/3/99235JAE[6%],MEK[12%]
237
Assemble cell
3 daysWed 8/4/99Fri 8/6/99236JAE[25%]
238
Mech att sec to post
2 daysMon 8/9/99Tue 8/10/99237JAE[12%]
239
Stifness tests
15 daysWed 8/11/99Tue 8/31/99238JAE[3%],Mwi[3%]
240
Contingency
20 daysWed 9/1/99Tue 9/28/99239JAE[6%],MEK[6%]
241
Anodize small parts
10 daysWed 10/6/99Tue 10/19/99240MT[6%]
242
Final assembly
10 daysWed 10/20/99Tue 11/2/99241JAE[6%]
243
Secondary cell done
0 daysTue 11/2/99Tue 11/2/99242 
244
Glue secondary onto stud
5 daysTue 5/23/00Mon 5/29/00177MT[10%]
245
Make cover for top end
5 daysTue 5/30/00Mon 6/5/00244MEK[12%],JAE[3%]
246
Weld cover for inst head
5 daysTue 6/6/00Mon 6/12/00245Hamilton Mach
247
Contract with Hamilton
20 daysTue 5/9/00Tue 6/6/00246SFMRB[2%]
248
Machine cover
5 daysTue 6/13/00Mon 6/19/00246MEK[12%],JAE[3%]
249
Assemble cover
4 daysTue 6/20/00Fri 6/23/00248JAE[12%]
250
Design baffle extenders
2 daysMon 6/26/00Tue 6/27/00249JAE[25%]
251
Construct baff extend
5 daysWed 6/28/00Tue 7/4/00250MEK[12%],JAE[3%]
252      
253
FIBERS/CALIBRATION SYSTEMS
149 daysMon 8/16/99Thu 3/9/00  
254
Integrate guiding head
20 daysFri 10/1/99Thu 10/28/99 JAE[6%]
255
Design modifications
10 daysFri 10/29/99Thu 11/11/99254JAE[12%]
256
Manufacture modifications
20 daysFri 11/12/99Thu 12/9/99255MEK[6%],MW[6%]
257
Finish assembling head
10 daysFri 12/10/99Thu 12/23/99256JAE[12%]
258
Design pick-off mirror
5 daysFri 11/12/99Thu 11/18/99255JAE[12%]
259
Build pick-off mirror
10 daysFri 11/19/99Thu 12/2/99258MEK[20%]
260
Set up guide camera
2 daysMon 8/16/99Tue 8/17/99 AH[25%]
261
Run guide camera under Linux
60 daysWed 8/18/99Tue 11/9/99260AH[25%]
262
Test in telescope
20 daysWed 11/10/99Tue 12/7/99261JAE[12%]
263
Procure fibers
40 daysFri 10/1/99Thu 11/25/99 FF[3%]
264
Design couplings
5 daysFri 11/26/99Thu 12/2/99263JAE[12%],SB[12%]
265
Contract for couplings
40 daysFri 12/3/99Thu 1/27/00264JAE[5%],MRB[5%]
266
Assemble signal fibers
30 daysFri 1/28/00Thu 3/9/00265SB[10%]
267
Decide on light source
20 daysFri 10/1/99Thu 10/28/99 JAE[12%],FF[12%]
268
Design coupling
15 daysFri 10/29/99Thu 11/18/99267JAE[20%],FF[12%]
269
Procure parts
30 daysFri 11/19/99Thu 12/30/99268MRB[5%],JAE[1%]
270
Make other parts
10 daysFri 12/31/99Thu 1/13/00269MEK[20%]
271
Assemble source bench
30 daysFri 1/14/00Thu 2/24/00270JAE[12%],FF[10%]
272      
273
PREPARE DATA HANDLING
354 daysTue 6/1/99Fri 10/6/00  
274
Establish internet link to tel
250 daysTue 6/1/99Mon 5/15/00 LJB[1%],WS[1%]
275
Simulate data from spectrograph
10 daysMon 11/1/99Fri 11/12/99 JAE[12%],FF[12%]
276
Adapt reduction system
60 daysMon 11/15/99Fri 2/4/00275FF[12%],JH[25%]
277
Contract
20 daysMon 10/18/99Mon 11/15/99276SFMRB[2%]
278
Script data system
20 daysMon 2/7/00Fri 3/3/00276FF[12%]
279
Simulate automatic reduction
30 daysMon 3/6/00Fri 4/14/00278FF[25%]
280
Ready to process data
1 dayMon 4/17/00Mon 4/17/00279 
281
Lab sim. With CCD
90 daysMon 5/8/00Fri 9/8/00280,153FF[6%]
282
Integrate data storage system
20 daysMon 9/11/00Fri 10/6/00281CW[12%]
283
Procure storage system
20 daysMon 4/10/00Mon 5/8/00281SFMRB[3%],FF[3%]