Project Start Date: Tue 6/1/99
Project Finish Date: Thu 4/12/01
| ID | Name | Duration | Start_Date | Finish_Date | Predecessors | Resource_Names |
|---|---|---|---|---|---|---|
| 1 | ||||||
| 2 | OVERHEAD | 481 days | Fri 5/28/99 | Fri 3/30/01 | ||
| 3 | Writing reports | 300 days | Tue 6/1/99 | Mon 7/24/00 | JAE[1%] | |
| 4 | Monthly reports | 436 days | Fri 7/30/99 | Fri 3/30/01 | ||
| 5 | Monthly reports 1 | 1 day | Fri 7/30/99 | Fri 7/30/99 | ||
| 6 | Monthly reports 2 | 1 day | Fri 8/27/99 | Fri 8/27/99 | ||
| 7 | Monthly reports 3 | 1 day | Fri 9/24/99 | Fri 9/24/99 | ||
| 8 | Monthly reports 4 | 1 day | Fri 10/29/99 | Fri 10/29/99 | ||
| 9 | Monthly reports 5 | 1 day | Fri 11/26/99 | Fri 11/26/99 | ||
| 10 | Monthly reports 6 | 1 day | Fri 12/31/99 | Fri 12/31/99 | ||
| 11 | Monthly reports 7 | 1 day | Fri 1/28/00 | Fri 1/28/00 | ||
| 12 | Monthly reports 8 | 1 day | Fri 2/25/00 | Fri 2/25/00 | ||
| 13 | Monthly reports 9 | 1 day | Fri 3/31/00 | Fri 3/31/00 | ||
| 14 | Monthly reports 10 | 1 day | Fri 4/28/00 | Fri 4/28/00 | ||
| 15 | Monthly reports 11 | 1 day | Fri 5/26/00 | Fri 5/26/00 | ||
| 16 | Monthly reports 12 | 1 day | Fri 6/30/00 | Fri 6/30/00 | ||
| 17 | Monthly reports 13 | 1 day | Fri 7/28/00 | Fri 7/28/00 | ||
| 18 | Monthly reports 14 | 1 day | Fri 8/25/00 | Fri 8/25/00 | ||
| 19 | Monthly reports 15 | 1 day | Fri 9/29/00 | Fri 9/29/00 | ||
| 20 | Monthly reports 16 | 1 day | Fri 10/27/00 | Fri 10/27/00 | ||
| 21 | Monthly reports 17 | 1 day | Fri 11/24/00 | Fri 11/24/00 | ||
| 22 | Monthly reports 18 | 1 day | Fri 12/29/00 | Fri 12/29/00 | ||
| 23 | Monthly reports 19 | 1 day | Fri 1/26/01 | Fri 1/26/01 | ||
| 24 | Monthly reports 20 | 1 day | Fri 2/23/01 | Fri 2/23/01 | ||
| 25 | Monthly reports 21 | 1 day | Fri 3/30/01 | Fri 3/30/01 | ||
| 26 | June 1999 review | 1 day | Tue 6/29/99 | Tue 6/29/99 | JAE[50%],MRB[50%] | |
| 27 | Write reports | 15 days | Tue 6/8/99 | Tue 6/29/99 | 26SF | JAE[25%],MRB[25%] |
| 28 | Hiring technicians | 20 days | Mon 7/5/99 | Fri 7/30/99 | JAE[6%],MRB[6%] | |
| 29 | Hiring instrumentalist/programmer | 40 days | Mon 7/5/99 | Fri 8/27/99 | JAE[3%],MRB[3%] | |
| 30 | Assess spare parts | 20 days | Mon 8/2/99 | Fri 8/27/99 | JAE[3%],MRB[3%] | |
| 31 | Travel for JAE | 221 days | Fri 5/28/99 | Fri 3/31/00 | ||
| 32 | Trip to California | 3 days | Fri 5/28/99 | Tue 6/1/99 | JAE | |
| 33 | July vacation | 1 day | Fri 7/9/99 | Fri 7/9/99 | JAE | |
| 34 | Trip to Arizona | 5 days | Mon 8/16/99 | Fri 8/20/99 | JAE | |
| 35 | January vacation | 5 days | Mon 1/3/00 | Fri 1/7/00 | JAE | |
| 36 | Telescopes conference? | 5 days | Mon 3/27/00 | Fri 3/31/00 | JAE | |
| 37 | Relocate telescope to Franklin | 42 days | Thu 6/17/99 | Fri 8/13/99 | ||
| 38 | Take telescope apart | 3 days | Mon 7/5/99 | Wed 7/7/99 | JAE[50%],MT[50%] | |
| 39 | Put on pads | 8 days | Thu 7/8/99 | Mon 7/19/99 | 38 | JAE[50%],MT[50%] |
| 40 | Add guards to parts | 2 days | Tue 7/20/99 | Wed 7/21/99 | 39 | JAE[33%] |
| 41 | Transport to Armory | 5 days | Thu 7/22/99 | Wed 7/28/99 | 40 | Continential |
| 42 | Contract for moving | 10 days | Thu 6/17/99 | Thu 7/1/99 | 41SF-15 days | MRB[5%] |
| 43 | Contract for space | 10 days | Thu 6/17/99 | Thu 7/1/99 | 41SF-15 days | MRB[5%] |
| 44 | Telescope relocated | 0 days | Wed 7/28/99 | Wed 7/28/99 | 41 | |
| 45 | Set up telescope base | 10 days | Mon 8/2/99 | Fri 8/13/99 | 44FS+2 days | JAE[20%],MT[20%] |
| 46 | Arrange electric service | 10 days | Mon 7/5/99 | Mon 7/19/99 | 45SF-10 days | MRB[5%] |
| 47 | Begin operations | 0 days | Thu 3/1/01 | Thu 3/1/01 | 216 | |
| 48 | ||||||
| 49 | FINISH ENCLOSURES | 240 days | Tue 6/1/99 | Mon 5/1/00 | ||
| 50 | Design building control | 30 days | Thu 7/1/99 | Wed 8/11/99 | LJB[10%] | |
| 51 | Build building control | 30 days | Thu 8/12/99 | Wed 9/22/99 | 50 | LJB[10%] |
| 52 | Paint concrete floors | 30 days | Tue 6/15/99 | Mon 7/26/99 | LJB[10%],contractor | |
| 53 | Cure paint before using | 30 days | Tue 7/27/99 | Mon 9/6/99 | 52 | |
| 54 | Enclosure ready for telescope | 0 days | Mon 9/6/99 | Mon 9/6/99 | 53 | |
| 55 | UPS/Wiring | 65 days | Tue 6/1/99 | Mon 8/30/99 | ||
| 56 | Accept bid for UPS | 1 day | Tue 6/1/99 | Tue 6/1/99 | JAE[5%],MRB[5%] | |
| 57 | Arrange delivery | 40 days | Wed 6/2/99 | Tue 7/27/99 | 56 | MRB[5%],SM[6%] |
| 58 | Get UPS to site | 10 days | Wed 7/28/99 | Tue 8/10/99 | 57 | LJB[5%],SM[20%] |
| 59 | Contact Sierrita | 20 days | Wed 6/30/99 | Wed 7/28/99 | 58SF | MRB[3%] |
| 60 | Wiring in building | 14 days | Wed 8/11/99 | Mon 8/30/99 | 58 | LJB[10%],electrician[25%] |
| 61 | Enclosure ready for tests | 0 days | Mon 8/30/99 | Mon 8/30/99 | 60 | |
| 62 | Modify/Insulate control buildings | 65 days | Tue 2/1/00 | Mon 5/1/00 | ||
| 63 | Design | 20 days | Tue 2/1/00 | Mon 2/28/00 | JAE[2%],LJB[6%] | |
| 64 | Glue in place | 20 days | Tue 3/28/00 | Mon 4/24/00 | 63FS+20 days | LJB[5%],SM[25%] |
| 65 | Insulation contract | 30 days | Tue 2/15/00 | Tue 3/28/00 | 64SF | MRB[2%],JAE[2%] |
| 66 | Place air conditioners&ducts | 3 days | Tue 4/25/00 | Thu 4/27/00 | 64 | LJB[5%],SM[25%] |
| 67 | Wire in air conditioner | 2 days | Fri 4/28/00 | Mon 5/1/00 | 66 | LJB[33%],electrician |
| 68 | Ready for spectrograph | 0 days | Mon 5/1/00 | Mon 5/1/00 | 67 | |
| 69 | ||||||
| 70 | FINISH MECHANICAL INTEGRATION | 113 days | Wed 6/2/99 | Fri 11/5/99 | ||
| 71 | Assemble drive tractors | 2 days | Wed 6/2/99 | Thu 6/3/99 | JAE[33%] | |
| 72 | Put drive tractors in telescope | 2 days | Fri 6/4/99 | Mon 6/7/99 | 71 | JAE[25%] |
| 73 | Adjust clamps and hardware | 15 days | Tue 6/8/99 | Mon 6/28/99 | 72 | JAE[12%] |
| 74 | Modify fittings | 5 days | Thu 7/8/99 | Wed 7/14/99 | 73FS+7 days | MEK[12%] |
| 75 | Finish adjusting clamps | 5 days | Mon 8/23/99 | Fri 8/27/99 | 74,45FS+5 days | JAE[25%] |
| 76 | Make cables for amplifiers | 5 days | Fri 6/4/99 | Thu 6/10/99 | 71 | AH[25%] |
| 77 | Contingency for modifying attachments | 60 days | Mon 8/16/99 | Fri 11/5/99 | 45 | JAE[1%],MEK[6%] |
| 78 | Make jig for gluing puck | 2 days | Wed 6/2/99 | Thu 6/3/99 | JAE[12%] | |
| 79 | Glue hard-pt puck back on | 4 days | Fri 6/4/99 | Wed 6/9/99 | 78 | JAE[6%] |
| 80 | Attach hard points | 4.5 days | Thu 6/10/99 | Wed 6/16/99 | 79 | JAE[8%] |
| 81 | Finish attachments for lat supp | 12 days | Wed 6/16/99 | Fri 7/2/99 | 80 | MEK[10%] |
| 82 | Integrate base skirt | 3 days | Tue 6/29/99 | Thu 7/1/99 | 73SS+10 days | JAE[25%] |
| 83 | Insulate exposed surfaces | 40 days | Wed 6/30/99 | Tue 8/24/99 | JAE[1%],KMD[3%],MT[1%] | |
| 84 | Construct wiring harnesses | 40 days | Wed 6/30/99 | Tue 8/24/99 | MT[12%],JAE[12%] | |
| 85 | Buy cables and connectors | 5 days | Wed 6/23/99 | Wed 6/30/99 | 84SF | AH[10%],JAE[10%] |
| 86 | Make power cables | 2 days | Mon 8/16/99 | Tue 8/17/99 | 85,45 | JAE[25%] |
| 87 | Set ampl. In torque mode | 2 days | Wed 8/18/99 | Thu 8/19/99 | 86 | MT[12%] |
| 88 | Put amplifiers into telescope | 1 day | Fri 8/20/99 | Fri 8/20/99 | 87 | JAE[12%],MT[25%] |
| 89 | Test amplifiers for motion | 2 days | Thu 9/30/99 | Fri 10/1/99 | 88,95 | JAE[25%] |
| 90 | Decide on anodizing sector | 5 days | Wed 6/23/99 | Tue 6/29/99 | JAE[6%] | |
| 91 | Find shop to anodize | 3 days | Wed 6/30/99 | Fri 7/2/99 | 90 | JAE[12%] |
| 92 | Run test piece | 5 days | Mon 7/5/99 | Fri 7/9/99 | 91 | JAE[3%] |
| 93 | Transport sector | 2 days | Tue 7/20/99 | Wed 7/21/99 | 39,92 | |
| 94 | Get sector anodized | 30 days | Thu 7/22/99 | Wed 9/1/99 | 93 | Outside shop |
| 95 | Finish assembling telescope | 20 days | Thu 9/2/99 | Wed 9/29/99 | 94 | JAE[20%],MT[20%] |
| 96 | Mech. Int.done | 0 days | Wed 9/29/99 | Wed 9/29/99 | 95 | |
| 97 | Redesign axial supports | 1 day | Thu 7/1/99 | Thu 7/1/99 | JAE[12%],MEK[12%] | |
| 98 | Purchase material | 2 days | Fri 7/2/99 | Mon 7/5/99 | 97 | JAE[12%],GD[12%] |
| 99 | Finish modification | 5 days | Tue 7/6/99 | Mon 7/12/99 | 98 | MEK[25%] |
| 100 | Add aux. Oil return system | 4 days | Thu 7/29/99 | Tue 8/3/99 | 41 | JAE[50%] |
| 101 | Wire up oil-pump control | 2 days | Tue 7/27/99 | Thu 7/29/99 | 100SF | JAE[12%],MT[12%] |
| 102 | Test aux oil return syst | 4 days | Wed 8/4/99 | Mon 8/9/99 | 100 | JAE[50%] |
| 103 | Buy plastic slugs | 3 days | Tue 7/27/99 | Fri 7/30/99 | 102SF-3 days | JAE[6%] |
| 104 | Contingency (oil ret) | 10 days | Tue 8/10/99 | Mon 8/23/99 | 102 | JAE[12%] |
| 105 | Cut clearances in parts | 2 days | Thu 7/29/99 | Fri 7/30/99 | 41 | JAE[25%],MEK[25%] |
| 106 | Center top end | 3 days | Mon 8/2/99 | Wed 8/4/99 | 105 | JAE[25%],KMD[25%] |
| 107 | Finish mirror-washing dam | 4 days | Thu 7/29/99 | Tue 8/3/99 | 41 | JAE[12%] |
| 108 | Machine dam fittings | 2 days | Tue 7/27/99 | Thu 7/29/99 | 107SF | JAE[12%] |
| 109 | Boxes for electronics | 20 days | Mon 8/16/99 | Fri 9/10/99 | 45 | JAE[3%],Hamilton? |
| 110 | Contract | 10 days | Mon 8/2/99 | Mon 8/16/99 | 109SF | MRB[3%],JAE[3%] |
| 111 | Design boxes | 5 days | Mon 7/26/99 | Mon 8/2/99 | 110SF | JAE[12%] |
| 112 | ||||||
| 113 | TEST PRIMARY MIRROR | 195 days | Wed 6/2/99 | Tue 2/29/00 | ||
| 114 | Contact optical consultant | 3 days | Wed 6/2/99 | Fri 6/4/99 | JAE+MRB contact R. Parks | |
| 115 | Obtain and review report | 5 days | Mon 6/7/99 | Fri 6/11/99 | 114 | RP[10%],JAE[5%] |
| 116 | Discuss project with Jim Bilbro | 1 day | Wed 6/2/99 | Wed 6/2/99 | JAE[25%],MRB[25%] | |
| 117 | Decide how MSFC can help here | 10 days | Thu 6/3/99 | Wed 6/16/99 | 116 | JAE[10%],MRB[10%] |
| 118 | Set up test with Scott Smith | 2 days | Thu 6/17/99 | Fri 6/18/99 | 117 | JAE[10%],MRB[12%] |
| 119 | Run test | 2 days | Thu 9/30/99 | Fri 10/1/99 | 95 | JAE[50%],SS[50%] |
| 120 | Finish setting up | 6 days | Wed 9/22/99 | Thu 9/30/99 | 119SF | JAE[12%] |
| 121 | Decide how to proceed | 10 days | Mon 10/4/99 | Fri 2/25/00 | 119 | JAE[25%] |
| 122 | Write report on results | 2 days | Mon 2/28/00 | Tue 2/29/00 | 121 | JAE[25%] |
| 123 | End mirror testing | 0 days | Tue 2/29/00 | Tue 2/29/00 | 122 | |
| 124 | Rough loading calculation | 2 days | Mon 6/14/99 | Tue 6/15/99 | MW[25%] | |
| 125 | Calculate effects of support | 40 days | Thu 7/1/99 | Wed 8/25/99 | AK[25%],JAE[1%] | |
| 126 | Reauthorize ANSYS | 15 days | Thu 6/10/99 | Thu 7/1/99 | 125SF | MRB[2%] |
| 127 | ||||||
| 128 | SET TELESCOPE UP AT SITE | 61 days | Mon 11/8/99 | Mon 1/31/00 | ||
| 129 | Take telescope apart | 3 days | Mon 11/8/99 | Wed 11/10/99 | 77 | JAE[50%],MT[50%] |
| 130 | Put on pads | 4 days | Thu 11/11/99 | Tue 11/16/99 | 129 | JAE[50%],MT[50%] |
| 131 | Contingency for modifications | 20 days | Wed 11/17/99 | Tue 12/14/99 | 130 | JAE[2%] |
| 132 | Transport to Arizona | 5 days | Wed 12/15/99 | Tue 12/21/99 | 131 | Continential |
| 133 | Establish contract for shipping | 20 days | Wed 11/17/99 | Wed 12/15/99 | 132SF | MRB[5%] |
| 134 | Set up telescope at WC | 7 days | Wed 1/12/00 | Thu 1/20/00 | 132FS+7 days,35FS+2 days | JAE[50%],LJB[50%],AH[50%] |
| 135 | Travel to Arizona | 2 days | Mon 1/10/00 | Wed 1/12/00 | 134SF | JAE |
| 136 | Arrange staging+ trans to WC | 20 days | Wed 12/15/99 | Wed 1/12/00 | 134SF | MRB[5%] |
| 137 | Contingency | 5 days | Fri 1/21/00 | Thu 1/27/00 | 134 | JAE[50%],LJB[50%],AH[50%] |
| 138 | Telescope on site | 0 days | Thu 1/27/00 | Thu 1/27/00 | 137 | |
| 139 | Travel to Nashville | 2 days | Fri 1/28/00 | Mon 1/31/00 | 138 | JAE[50%] |
| 140 | ||||||
| 141 | GET CCD CONTROLLERS | 219 days | Tue 7/6/99 | Fri 5/5/00 | ||
| 142 | Contact SDSU for latest spec | 3 days | Tue 7/6/99 | Thu 7/8/99 | JAE[10%] | |
| 143 | Establish contract | 60 days | Fri 7/23/99 | Thu 10/14/99 | 142FS+10 days | MRB[3%],JAE[3%] |
| 144 | Start controller contract | 0 days | Thu 10/14/99 | Thu 10/14/99 | 143 | |
| 145 | Receive controller | 80 days | Fri 11/12/99 | Thu 3/2/00 | 143FS+20 days | JAE[2%] |
| 146 | Procure control computer | 45 days | Fri 9/24/99 | Thu 11/25/99 | 145SF+10 days | MRB[2%],JAE[2%] |
| 147 | Computer contract | 30 days | Fri 8/13/99 | Fri 9/24/99 | 146SF | MRB[3%],JAE[3%] |
| 148 | Training at SDSU | 5 days | Fri 2/18/00 | Thu 2/24/00 | 145FF-5 days | JAE[50%],AH[50%] |
| 149 | Ship to Nashville | 10 days | Fri 3/3/00 | Thu 3/16/00 | 145 | |
| 150 | Receive controller | 0 days | Thu 3/16/00 | Thu 3/16/00 | 149 | |
| 151 | Test CCD system in lab | 30 days | Fri 3/17/00 | Thu 4/27/00 | 149 | AH[25%],JAE[12%] |
| 152 | Integrate into control system | 6 days | Fri 4/28/00 | Fri 5/5/00 | 151 | AH[25%] |
| 153 | Ready for data tests | 0 days | Fri 5/5/00 | Fri 5/5/00 | 152 | |
| 154 | ||||||
| 155 | WRITE/TEST CONTROL SYSTEM | 384 days | Wed 6/2/99 | Mon 11/20/00 | ||
| 156 | Write functions for timing | 1 day | Wed 6/2/99 | Wed 6/2/99 | JAE+students | |
| 157 | Write functions for coord conv | 1 day | Wed 6/2/99 | Wed 6/2/99 | JAE+students | |
| 158 | Write functions for communication | 60 days | Thu 6/3/99 | Wed 8/25/99 | 157 | JAE[12%],AH[12%] |
| 159 | Write basic device drivers | 60 days | Thu 6/3/99 | Wed 8/25/99 | 157 | AH[16%] |
| 160 | Implement servo loop | 30 days | Thu 8/26/99 | Wed 10/6/99 | 159 | JAE[12%],AH[12%] |
| 161 | Write serial daemons | 20 days | Sun 8/1/99 | Fri 8/27/99 | JAE[12%] | |
| 162 | Test with steppers | 30 days | Mon 8/30/99 | Fri 10/8/99 | 161 | JAE[8%] |
| 163 | Wire up stepper controllers | 30 days | Mon 7/19/99 | Mon 8/30/99 | 162SF | JAE[5%],Students |
| 164 | Make bases for controllers | 5 days | Mon 7/12/99 | Mon 7/19/99 | 163SF | JAE[3%],MEK[12%] |
| 165 | Acquire stepper controllers | 30 days | Mon 6/7/99 | Mon 7/19/99 | 163SF | MRB[3%] |
| 166 | Test with IO modules | 9.86 days | Mon 8/30/99 | Fri 9/10/99 | 161 | JAE[12%],Mwi[25%] |
| 167 | Acquire IO modules | 30 days | Mon 7/19/99 | Mon 8/30/99 | 166SF | MRB[3%] |
| 168 | Tests of basic AZ/ZD motions | 15 days | Thu 9/30/99 | Wed 10/20/99 | 95 | JAE[12%],AH[12%] |
| 169 | Test limits, ZP's | 10 days | Thu 10/21/99 | Wed 11/3/99 | 168 | JAE[12%],AH[12%] |
| 170 | Basic tests done | 0 days | Wed 11/3/99 | Wed 11/3/99 | 169 | |
| 171 | Set up Apogee cam in lab | 20 days | Thu 9/2/99 | Wed 9/29/99 | 159FS+5 days | Mwi[25%] |
| 172 | Put Apogee cam in tel | 20 days | Tue 2/29/00 | Mon 3/27/00 | 139FS+20 days | AH[12%],JAE[12%] |
| 173 | Implement control computer | 10 days | Tue 2/29/00 | Mon 3/13/00 | 139FS+20 days | AH[12%],JAE[12%] |
| 174 | Control-computer contract | 30 days | Tue 1/18/00 | Tue 2/29/00 | 173SF | MRB[2%],AH[5%],JAE[3%] |
| 175 | Begin tracking tests | 0 days | Mon 3/27/00 | Mon 3/27/00 | 172 | |
| 176 | Initial tracking tests | 20 days | Tue 3/28/00 | Mon 4/24/00 | 175 | JAE[12%],AH[12%] |
| 177 | Test image quality | 20 days | Tue 4/25/00 | Mon 5/22/00 | 176 | JAE[5%],AH[5%] |
| 178 | Verify stepper controls | 20 days | Tue 4/25/00 | Mon 5/22/00 | 176 | JAE[12%],AH[12%] |
| 179 | Assess tracking/images | 20 days | Tue 5/23/00 | Mon 6/19/00 | 178 | JAE[25%] |
| 180 | Detailed tracking tests | 30 days | Tue 6/20/00 | Mon 7/31/00 | 179 | JAE[12%],AH[12%] |
| 181 | Assess guiding strategy | 30 days | Tue 8/1/00 | Mon 9/11/00 | 180 | JAE[25%],AH[25%] |
| 182 | Contingency | 30 days | Tue 9/12/00 | Mon 10/23/00 | 181 | JAE[12%],AH[12%] |
| 183 | End tracking tests | 0 days | Mon 10/23/00 | Mon 10/23/00 | 182 | |
| 184 | Implement scheduler | 20 days | Tue 10/24/00 | Mon 11/20/00 | 183 | AH[25%],DE[25%] |
| 185 | ||||||
| 186 | FINISH SPECTROGRAPH | 488 days | Tue 6/1/99 | Thu 4/12/01 | ||
| 187 | Have prelim designs of spectrograph | 1 day | Tue 6/1/99 | Tue 6/1/99 | JAE[50%] | |
| 188 | Retain optical designer | 30 days | Wed 6/2/99 | Tue 7/13/99 | 187 | MRB[2%],JAE[1%] |
| 189 | Begin formal design | 0 days | Tue 7/13/99 | Tue 7/13/99 | 188 | |
| 190 | Prelim design of spect | 20 days | Wed 7/14/99 | Tue 8/10/99 | 189 | DW[25%] |
| 191 | Prelim design of camera | 32 days | Wed 8/11/99 | Thu 9/23/99 | 190 | DW[25%] |
| 192 | Review results | 10 days | Fri 9/24/99 | Thu 10/7/99 | 191 | DW[12%],JAE[12%] |
| 193 | Contingency | 20 days | Fri 10/8/99 | Thu 11/4/99 | 192 | JAE[6%] |
| 194 | Have Maymon review | 20 days | Fri 11/5/99 | Thu 12/2/99 | 193 | JAE[10%] |
| 195 | Prelim design done | 0 days | Thu 12/2/99 | Thu 12/2/99 | 194 | |
| 196 | Final design of camera | 20 days | Fri 12/3/99 | Thu 12/30/99 | 195 | DW[12%] |
| 197 | Contingency | 20 days | Fri 12/31/99 | Thu 1/27/00 | 196 | |
| 198 | Design done | 0 days | Thu 1/27/00 | Thu 1/27/00 | 197 | |
| 199 | Get recommendations for optical shops | 10 days | Fri 11/5/99 | Thu 11/18/99 | 193 | JAE[12%] |
| 200 | Lens-cell contract | 30 days | Fri 11/19/99 | Thu 12/30/99 | 199 | MRB[2%],JAE[3%] |
| 201 | Design cell for lens | 20 days | Fri 12/31/99 | Thu 1/27/00 | 200 | JAE[12%],DW[12%],contractor[50%] |
| 202 | Get lens cell manufactured | 60 days | Fri 1/28/00 | Thu 4/20/00 | 201 | DW[5%] |
| 203 | Procure glass blanks for lens | 80 days | Fri 12/31/99 | Thu 4/20/00 | 196 | JAE[5%],MRB[5%] |
| 204 | Have lens manufactured | 120 days | Fri 4/21/00 | Thu 10/5/00 | 203 | DW[6%] |
| 205 | Lens manufactured | 0 days | Thu 10/5/00 | Thu 10/5/00 | 204 | |
| 206 | Get lenses coated | 60 days | Fri 10/6/00 | Thu 12/28/00 | 205 | DW[6%],JAE[6%] |
| 207 | Lens-coating contract | 30 days | Fri 8/25/00 | Fri 10/6/00 | 206SF | MRB[2%],JAE[3%] |
| 208 | Make mounts for optics | 30 days | Fri 4/21/00 | Thu 6/1/00 | 203 | Outside shop |
| 209 | Optic-mount contract | 30 days | Fri 3/10/00 | Fri 4/21/00 | 208SF | MRB[2%],JAE[3%] |
| 210 | Design mounts for optics | 60 days | Fri 12/17/99 | Fri 3/10/00 | 209SF | JAE[3%] |
| 211 | Have mirrors coated | 60 days | Fri 12/31/99 | Thu 3/23/00 | 196 | DW[6%],MRB[6%] |
| 212 | Mirror-coating contract | 12 days | Wed 12/15/99 | Fri 12/31/99 | 211SF | MRB[2%],JAE[3%] |
| 213 | Begin integration | 0 days | Thu 12/28/00 | Thu 12/28/00 | 206 | |
| 214 | Integrate spectrograph | 30 days | Fri 12/29/00 | Thu 2/8/01 | 213 | JAE[12%],AH[12%] |
| 215 | Test spectrograph | 15 days | Fri 2/9/01 | Thu 3/1/01 | 214 | JAE[12%],AH[12%] |
| 216 | Spectrogreph done | 0 days | Thu 3/1/01 | Thu 3/1/01 | 215 | |
| 217 | Set up on site | 30 days | Fri 3/2/01 | Thu 4/12/01 | 216 | JAE[12%],LJB[12%] |
| 218 | ||||||
| 219 | FINISH SMALL SYSTEMS | 286 days | Tue 6/1/99 | Tue 7/4/00 | ||
| 220 | Bid + order abs encoders | 1 day | Wed 6/2/99 | Wed 6/2/99 | MRB[0%] | |
| 221 | Procure encoders | 10 days | Thu 6/3/99 | Wed 6/16/99 | 220 | MRB[2%] |
| 222 | Finish mount for AZ encoder | 10 days | Tue 6/1/99 | Mon 6/14/99 | 221 | MW[84%],MEK[5%] |
| 223 | Finish mount for ZD encoder | 5 days | Tue 6/8/99 | Mon 6/21/99 | 222 | MW[25%] |
| 224 | Integrate encoders into mounts | 6 days | Mon 6/21/99 | Tue 6/29/99 | 223 | JAE[25%],MW[25%] |
| 225 | Make up drive cable | 3 days | Tue 6/29/99 | Fri 7/2/99 | 224 | MW[12%] |
| 226 | Modify driven wheel | 4 days | Fri 7/2/99 | Thu 7/8/99 | 225 | JAE[6%],MT[25%] |
| 227 | Assemble encoder mounts | 4 days | Thu 7/8/99 | Wed 7/14/99 | 226 | JAE[6%] |
| 228 | Contingency | 10 days | Wed 7/14/99 | Wed 7/28/99 | 227 | JAE[3%],MEK[6%] |
| 229 | Encoder mounts done | 0 days | Wed 7/28/99 | Wed 7/28/99 | 228 | |
| 230 | Modify sec mirror cell | 1 day | Wed 6/16/99 | Wed 6/16/99 | MW[25%] | |
| 231 | Build flexures | 2 days | Thu 6/17/99 | Fri 6/18/99 | 230 | MW[25%] |
| 232 | Modify attachments | 2 days | Mon 6/21/99 | Tue 6/22/99 | 231 | MW[25%] |
| 233 | Build pulls | 5 days | Wed 6/23/99 | Tue 6/29/99 | 232 | MW[12%] |
| 234 | Modify flexures | 5 days | Wed 6/30/99 | Tue 7/6/99 | 233 | JAE[6%],MEK[25%] |
| 235 | Add limit switches | 5.83 days | Wed 7/7/99 | Wed 7/14/99 | 234 | JAE[6%],Mwi[12%] |
| 236 | Further mod sec cell | 15 days | Wed 7/14/99 | Tue 8/3/99 | 235 | JAE[6%],MEK[12%] |
| 237 | Assemble cell | 3 days | Wed 8/4/99 | Fri 8/6/99 | 236 | JAE[25%] |
| 238 | Mech att sec to post | 2 days | Mon 8/9/99 | Tue 8/10/99 | 237 | JAE[12%] |
| 239 | Stifness tests | 15 days | Wed 8/11/99 | Tue 8/31/99 | 238 | JAE[3%],Mwi[3%] |
| 240 | Contingency | 20 days | Wed 9/1/99 | Tue 9/28/99 | 239 | JAE[6%],MEK[6%] |
| 241 | Anodize small parts | 10 days | Wed 10/6/99 | Tue 10/19/99 | 240 | MT[6%] |
| 242 | Final assembly | 10 days | Wed 10/20/99 | Tue 11/2/99 | 241 | JAE[6%] |
| 243 | Secondary cell done | 0 days | Tue 11/2/99 | Tue 11/2/99 | 242 | |
| 244 | Glue secondary onto stud | 5 days | Tue 5/23/00 | Mon 5/29/00 | 177 | MT[10%] |
| 245 | Make cover for top end | 5 days | Tue 5/30/00 | Mon 6/5/00 | 244 | MEK[12%],JAE[3%] |
| 246 | Weld cover for inst head | 5 days | Tue 6/6/00 | Mon 6/12/00 | 245 | Hamilton Mach |
| 247 | Contract with Hamilton | 20 days | Tue 5/9/00 | Tue 6/6/00 | 246SF | MRB[2%] |
| 248 | Machine cover | 5 days | Tue 6/13/00 | Mon 6/19/00 | 246 | MEK[12%],JAE[3%] |
| 249 | Assemble cover | 4 days | Tue 6/20/00 | Fri 6/23/00 | 248 | JAE[12%] |
| 250 | Design baffle extenders | 2 days | Mon 6/26/00 | Tue 6/27/00 | 249 | JAE[25%] |
| 251 | Construct baff extend | 5 days | Wed 6/28/00 | Tue 7/4/00 | 250 | MEK[12%],JAE[3%] |
| 252 | ||||||
| 253 | FIBERS/CALIBRATION SYSTEMS | 149 days | Mon 8/16/99 | Thu 3/9/00 | ||
| 254 | Integrate guiding head | 20 days | Fri 10/1/99 | Thu 10/28/99 | JAE[6%] | |
| 255 | Design modifications | 10 days | Fri 10/29/99 | Thu 11/11/99 | 254 | JAE[12%] |
| 256 | Manufacture modifications | 20 days | Fri 11/12/99 | Thu 12/9/99 | 255 | MEK[6%],MW[6%] |
| 257 | Finish assembling head | 10 days | Fri 12/10/99 | Thu 12/23/99 | 256 | JAE[12%] |
| 258 | Design pick-off mirror | 5 days | Fri 11/12/99 | Thu 11/18/99 | 255 | JAE[12%] |
| 259 | Build pick-off mirror | 10 days | Fri 11/19/99 | Thu 12/2/99 | 258 | MEK[20%] |
| 260 | Set up guide camera | 2 days | Mon 8/16/99 | Tue 8/17/99 | AH[25%] | |
| 261 | Run guide camera under Linux | 60 days | Wed 8/18/99 | Tue 11/9/99 | 260 | AH[25%] |
| 262 | Test in telescope | 20 days | Wed 11/10/99 | Tue 12/7/99 | 261 | JAE[12%] |
| 263 | Procure fibers | 40 days | Fri 10/1/99 | Thu 11/25/99 | FF[3%] | |
| 264 | Design couplings | 5 days | Fri 11/26/99 | Thu 12/2/99 | 263 | JAE[12%],SB[12%] |
| 265 | Contract for couplings | 40 days | Fri 12/3/99 | Thu 1/27/00 | 264 | JAE[5%],MRB[5%] |
| 266 | Assemble signal fibers | 30 days | Fri 1/28/00 | Thu 3/9/00 | 265 | SB[10%] |
| 267 | Decide on light source | 20 days | Fri 10/1/99 | Thu 10/28/99 | JAE[12%],FF[12%] | |
| 268 | Design coupling | 15 days | Fri 10/29/99 | Thu 11/18/99 | 267 | JAE[20%],FF[12%] |
| 269 | Procure parts | 30 days | Fri 11/19/99 | Thu 12/30/99 | 268 | MRB[5%],JAE[1%] |
| 270 | Make other parts | 10 days | Fri 12/31/99 | Thu 1/13/00 | 269 | MEK[20%] |
| 271 | Assemble source bench | 30 days | Fri 1/14/00 | Thu 2/24/00 | 270 | JAE[12%],FF[10%] |
| 272 | ||||||
| 273 | PREPARE DATA HANDLING | 354 days | Tue 6/1/99 | Fri 10/6/00 | ||
| 274 | Establish internet link to tel | 250 days | Tue 6/1/99 | Mon 5/15/00 | LJB[1%],WS[1%] | |
| 275 | Simulate data from spectrograph | 10 days | Mon 11/1/99 | Fri 11/12/99 | JAE[12%],FF[12%] | |
| 276 | Adapt reduction system | 60 days | Mon 11/15/99 | Fri 2/4/00 | 275 | FF[12%],JH[25%] |
| 277 | Contract | 20 days | Mon 10/18/99 | Mon 11/15/99 | 276SF | MRB[2%] |
| 278 | Script data system | 20 days | Mon 2/7/00 | Fri 3/3/00 | 276 | FF[12%] |
| 279 | Simulate automatic reduction | 30 days | Mon 3/6/00 | Fri 4/14/00 | 278 | FF[25%] |
| 280 | Ready to process data | 1 day | Mon 4/17/00 | Mon 4/17/00 | 279 | |
| 281 | Lab sim. With CCD | 90 days | Mon 5/8/00 | Fri 9/8/00 | 280,153 | FF[6%] |
| 282 | Integrate data storage system | 20 days | Mon 9/11/00 | Fri 10/6/00 | 281 | CW[12%] |
| 283 | Procure storage system | 20 days | Mon 4/10/00 | Mon 5/8/00 | 281SF | MRB[3%],FF[3%] |